Emergency Services Expansion update 

Click here to read an update about the Emergency Services Expansion.

On Wednesday, April 24, and Thursday, April 25, a drilling rig will be mobilized to drill bore holes in the east side hospital exterior, parking lot, and north of the hospital. This will result in vibration and noise. Drilling will happen during standard business hours. 

Please ensure patients are offered earplugs or other amenities to keep them comfortable during this process. The drilling rig will look similar to the photo below.

On April 15, construction crews began demolition of the former Dental entrance, which will remain closed through August 2024. This is no longer an entrance or exit to the facility, and Interim Life Safety Measures and plans will be implemented throughout the duration of the phase. Once the Temporary ED opens, this south entrance will become a staff entrance through the project completion.

Coming Up
The demolition of the former Dental entrance octagon and east side exterior canopy is scheduled for early May. Demolition of the octagon and canopy will take place during standard business hours. During demolition, traffic will be rerouted around the fenced area which is reflected by the blue dotted line in the image below. Please watch for rerouted traffic patterns around construction activities.

Parking Update
Starting on Friday, April 26, construction crews will take over more of the ANMC hospital east side parking lot for construction staging. The east lot parking is reserved for patients. Please park in designated staff parking areas.